Projects

Quick project outcomes with optional STARL context by card.

SPC Extrusion Standardization Reset

Mohawk • Senior Manager

Details

Standardized day to day extrusion operations to stabilize safety and quality and unlock throughput.

  • Average monthly rejects improved from 12% to 6%; two consecutive benchmark months at 5% loss
  • Throughput increased from 50K to 60K sqft/day; reported annual production increase of 15M sqft
  • $3.6M projected annual production/yield value; may overlap the reported $3.6M loss-reduction savings

Line 6 Flex LVT Startup (Operational Owner for Commissioning + Readiness)

Mohawk Industries, Resilient • Senior Manager

Details

As plant manager for SPC extrusion, owned operational readiness and accelerated commissioning and startup of Line 6, a new flexible LVT extrusion line, achieving saleable product within hours.

  • February 2025 startup of Line 6, first flexible LVT line (new product class versus existing rigid lines)
  • Commissioned in 1 day, ran capability and setpoint determination for 2 days
  • Achieved saleable product within about 6 hours of first material entering the extruder

LVT Lacquer Consumption Reset (Gap Control + Supplier-Led Root Cause)

Mohawk Industries, Resilient • Manager

Details

Cut lacquer consumption from 8 barrels per day to 4 to 5 by fixing gap control and curing stability instead of dumping tanks as a workaround.

  • Baseline lacquer consumption averaged 8 barrels per day for years
  • Reduced to 4 to 5 barrels per day after standardizing gap settings and preventing overclose
  • About 3.5 barrels per day reduction, about 360 days per year

Belt Press Teflon Belt Failure Reduction (RCA + Standard Work)

Mohawk • Senior Engineer

Details

Cut belt press Teflon belt replacements in half by preventing PVC contamination damage and tightening patching and edge-cleaning discipline.

  • 50% lower replacement rate; $750K annual savings tracked over four years
  • Bottom belt 121 m and top belt 96 m, about $1,000 per meter (about $120k bottom belt)
  • 2020 replacements: 14 top and 14 bottom
  • 2022 replacements: 7 top and 7 bottom (50% reduction)
  • Vendor theoretical best: 5 replacements per year
  • Achieved 6 top belt replacements in 2023

Lamination Lost-Batch Reduction (Vacuum Transport + Alarm Logic Fix)

Mohawk • Senior Engineer

Details

Reduced lost-batch events in lamination material handling by fixing vacuum transport conditions and eliminating automation alarm behavior that caused batch stops.

  • Over $1M annual savings in uptime and reduced startup waste
  • Eliminated a top-three downtime cost
  • Reported 90% lower material-cost loss; its measurement period is unspecified

LSS Black Belt Caustic Savings (Extraction Effluent Reuse)

RockTenn • Senior Engineer

Details

Reduced caustic consumption by reusing extraction effluent as makeup in an earlier bleaching stage, converting a waste stream into value.

  • $800K annual chemical savings from waste-stream reuse

Fiberglass Splice Wrinkle Reduction (Pull Roller Elimination + Splice Standardization)

Mohawk Industries, Resilient • Senior Engineer

Details

Cut fiberglass splice related tear-outs and wrinkle defects by removing a problematic pull roller and standardizing splice execution across shifts.

  • Reduced fiberglass splice related defects by about 50 percent in 2021 versus 2020

Settling Basin Chemistry Optimization (Polymer vs Alum Strategy)

Resolute • Superintendent

Details

Reduced total settling basin cost by shifting the chemistry strategy from alum-driven solids settling to a polymer-based approach, extending basin runtime and reducing cleanout burden.

  • $500K savings in reduced alum use (measurement period unconfirmed)
  • Reported about 50% longer settling-basin runtime
  • Implemented in 2017-09

Lime Kiln Fuel Cost Reduction (Mud Solids + Vacuum System Reliability)

Resolute • Superintendent

Details

Reduced kiln natural gas usage by increasing mud solids and stabilizing drum filter and vacuum pump performance.

  • Reduced kiln fuel cost by about $300K per year
  • Implemented in 2016-07

$3M Contractor RFQ and Outage Cleaning Governance (Hydroblasting + Confined Space)

Resolute Forest Products • Superintendent

Details

Owned annual RFQs and contractor selection for comprehensive mill cleaning services and outage execution, managing safety risk, schedule pressure, and scope change without schedule overruns from cleaning delays.

  • Managed annual RFQ and award for about $3M cleaning contract scope (hydroblasting, vac work, tank cleaning, confined space, scaffolding)
  • Ran outage cleaning scope governance with tight windows and no schedule overage due to delayed cleaning
  • Maintained strong contractor safety performance through standdowns, reviews, and enforcement (no crew removed for safety violations)

LSS Green Belt Chemical Savings (Automatic Titrators + MSA Fix)

RockTenn • Engineer

Details

Quantified and eliminated chemical loss driven by testing inefficiency by fixing the measurement system and upgrading titration.

  • $250K annual chemical savings from improved laboratory testing
  • Process Engineer project using DMAIC, MSA, and Poke Yoke